#108808
maoz
Participant

Hi, and thanks for the swift replay.

Let me explain exactly the senario:

We will create 4 events:

1 – from 9:00am to 12:00pm, 2 – from 9:30am to 10:00am, 3 – from 9:30am to 10:00am, 4 – from 10:00am to 10:30am.

Events 1, 2 and 3 share time and are displayed correctly.

Event 4 only shares time with event 1 so the expected behaviour is that event 1 will stay as is but event 4 will stretch to the end of the cell.

 

The following image is the correct behaviour.

 

The next image is the problem:  as explained event 4 only overlaps event 1 so it should stretch to the end of the cell. but it box shows as if there is a third event in the same time and there isn’t.

This is all done on the example smart scheduler. please let me know if you require further information.