  • #104717
    sj444
    Participant

    Hello,

    Is there a way to change the Gantt chart Timeline time format. I believe by default its 12h format. I want the same to be 24h. I saw a property “ganttchart.hourFormat” that accepts string values. But I’m not sure what value I should feed it to get the 24h format..

    Thanking in advance,

    SJ

    #104719
    Markov
    Keymaster

    Hi SJ,

    You can use the timelineHeaderFormatFunction property to customize and override the default header cells formatting of the Gantt.

    Regards,

    Markov

    #104720
    sj444
    Participant

    Hi,

    Got It.. Thank you